Under construction

Build progress

Foundation and slab are done (slab poured Sep 11, 2026). The second floor was framed by Oct 29, and the roof trusses are being set now.

Floor plans

From the architect's sheets A2.0 and A2.1, drawn at 3/16″ = 1′-0″. Areas are per room as labeled on the plans.

Sheet A2.0

First floor

Shop
2,556 sq ft
Shop (4-vehicle garage)
1,673 sq ft
Gym
1,305 sq ft
Rec room
713 sq ft
Covered patio
870 sq ft
Covered parking
862 sq ft
Storage (2)
353 + 318 sq ft
Utility, 2 half baths, elevator
Sheet A2.1

Second floor

Seating areas
600 + 362 sq ft
Covered deck, 2-sided fireplace
800 sq ft
Balcony over the rec room
408 sq ft
Offices (3)
214 · 268 · 240 sq ft
Art room
350 sq ft
Studio
319 sq ft
2 baths, closets, utility, elevator

Contact

Questions about the build or opening day.

Project lead
JF

Jeremy Foster

BarNGymCade

Follow along or reach out on LinkedIn for build updates and walkthroughs.

Connect on LinkedIn
linkedin.com/in/jeremyfostertech
Done so far
Site cleared and dug outDone
Footings with rebarDone
Column pads pouredDone
Foundation walls pouredDone
Slab pouredSep 11
Second floor framedOct 29
Roof trussesIn progress